Fort Stanton Water Line Replacement (NM)
Owner:
State of NM Cultural Affairs 407 Galisteo St. Bataan Memorial Build. Santa Fe, NM 87501
Type Of Work:
Contracted to replace the existing water system located around the main parade ground within the Ft. Stanton Historic site. Key factors included preserving historic elements of the site and maneuvering through unknown existing underground utilities. Scope of work included methodical excavation, installation of water line, fire hydrants, valves, water meters, backfill, asphalt paving.
Contract Number:
State Wide Price Agreement Contract
Current Contract Amount:
$1,047,475.90
Completion
June 2022